FIRST ARCHITECTURAL ESTIMATE
Congratulations!
PROJECT DESCRIPTION
Repair fire damage to second floor of existing 4-plex apartment building
and remodel interior — located at 3778 Shasta St., San Diego, CA
PROJECT ADDRESS
3778 Shasta St., San Diego, CA
PROPOSED USE
4-Unit Apartment Building (No Change)
The existing use is staying the same—no new units, no use change.
PROPOSED SQUARE FOOTAGE
3,006 SF
(No change)
You're not adding square footage—just repairing/remodeling.
ASSESSOR’S PARCEL NUMBER (APN)
424-553-22
ENVELOPE/FOOTPRINT
No change to non-conforming envelope
So, even if the building doesn't fully comply with current setbacks or codes, they're not increasing volume, so it's allowed to remain as is.
LEGAL DESCRIPTION
Lots 41 & 42 in Block 36 of Fortuna Park Addition, Map 894
Filed 1-22-03
ZONING
R-1500 Coastal Zone
(This likely refers to a multi-family residential zone with a density of 1 unit per 1,500 sq. ft.)
OCCUPANCY
R-1 (Standard residential occupancy type)
SHEET INDEX (Drawing Set Overview)
| Sheet | Description |
|---|---|
| 1 | Site Plan, Project Summary |
| 2 | Floor Plans |
| 3 | Exterior Elevations (East & West) |
| 4 | Exterior Elevations (North & South) |
| 5 | Demolition Plan |
| 6 | Foundation Plan, Roof Plan |
| 7 | Second Floor Framing, Roof Framing |
| 8 | Building Sections |
| 9 | Door and Finish Schedules |
| 10 | Window Schedule, Interior Elevations |
| 11 | Electrical Floor Plan |
| 12 | General Notes and Specifications |
| 13 | Construction Details |
Task:
-
Redraw or clean up this site plan professionally
-
Based on this layout and dimensions
-
Likely recreate it in CAD or similar format
-
Deliver it cleanly for city permitting or as part of a construction document set
Notes:
The sketch gives you layout, but not reliable, scaled dimensions of structures, walls, openings, elevations, or anything detailed enough for city approval.
Option 1: They Provide Original Plans or As-Builts
If the owner or city has original as-built drawings or older plans (e.g., from construction or previous permits), they might be able to give those to you.
You could redraw from that into a clean, city-ready plan.
Ask for this first.
Option 2: You Do a Site Visit and Measure
If no original plans exist or they're too outdated, you'll need to do a field measure of the structure.
That means measuring building walls, windows, doors, unit layouts, site boundaries (if unclear), and distances from property lines (setbacks).
You’ll likely need to bring a laser measurer, tape, and sketch pad or tablet.
Most likely:
-
There was significant fire damage to the second floor.
-
The city requires updated drawings to approve repair work.
-
Even if the building isn’t expanding or changing, they still need:
-
A clean site plan
-
Floor plans showing the rebuild
-
Possibly elevations, framing, and sections
-
All in permit-ready format, meeting current code and documentation standards
-
This is standard procedure when dealing with structural repairs, especially fire damage.
_______________________________________________
1. Project Scope Summary
Task: Redraw/clean up site plans and construction documents for fire-damaged 2nd floor of a 4-plex (3,006 SF).
Deliverables: 13-sheet set (site plan, floor plans, elevations, framing, schedules, etc.).
Key Constraints: No change to footprint/use, but permit-ready drawings required for repairs.
2. Estimated Timeline
Phase Duration Notes
1. Existing Conditions 1–3 weeks - If original as-builts are available: 1 week to digitize/update.
- If field measurement needed: 2–3 weeks (site visit + verification).
2. Redraw/CAD Drafting 2–4 weeks - Clean up floor plans, elevations, and site plan in CAD.
- Structural/framing details may require engineer coordination.
3. Demolition Plans 1 week - Outline fire-damaged areas to be removed (Sheet 5).
4. Code Compliance Review 1–2 weeks - Verify compliance with current San Diego codes (e.g., fire separation, egress).
5. Permit-Ready Set 1–2 weeks - Finalize sheets, notes, and specifications (Sheets 1–13).
Total (Optimistic) 6–8 weeks If as-builts exist and minimal revisions.
Total (Field Measure) 8–12 weeks If site visit + measurements required.
3. Critical Factors Affecting Timeline
As-Built Availability: Fastest if original plans are provided (saves 2–3 weeks).
Field Measurement Complexity: Irregular layouts or fire damage may prolong measurements.
City Feedback: San Diego’s permit review can add 4–12 weeks post-submission.
Engineer Coordination: Framing/structural details may need additional time.
4. Recommendations to Expedite
Request as-builts from the owner/city (Option 1) to avoid field measurements.
Use laser scanning (if budget allows) for accurate damaged-area documentation.
Parallel workflows: Start drafting unaffected areas while awaiting structural inputs.
Pre-submission meeting with San Diego Development Services to clarify requirements.
5. Permitting Note
Even with no footprint changes, San Diego may require:
Fire damage inspection reports.
Energy compliance (Title 24) for remodeled interiors.
Coastal Zone approvals (if applicable).
Let me know if you need a detailed workflow or vendor recommendations (e.g., surveyors, engineers).
____________________________________________________________________________
For an entry-level drafter working in Revit on this 4-plex repair/remodel project, here’s a realistic time estimate for completing the 13 sheets, focusing only on layout and plan design (excluding structural/engineering coordination, permitting, or major revisions):
Estimated Time Breakdown (Revit Drafting Only)
Sheet Task Time Estimate
Sheet 1: Site Plan Base map setup, property lines, annotations 4–6 hours
Sheet 2: Floor Plans Existing + proposed layouts (2 floors) 8–12 hours
Sheet 3–4: Elevations East/West/North/South (cleanup + detailing) 6–8 hours
Sheet 5: Demolition Plan Highlight fire-damaged areas 3–5 hours
Sheet 6: Foundation/Roof Basic roof plan + foundation outline 4–6 hours
Sheet 7: Framing Plans Simplified 2nd floor + roof framing 6–8 hours
Sheet 8: Building Sections 2–3 typical sections 4–6 hours
Sheet 9: Door/Finish Schedules Populate schedules 3–5 hours
Sheet 10: Window Schedules/Int. Elev. Window tags + cabinet elevations 5–7 hours
Sheet 11: Electrical Plan Outlets, switches, lighting (basic) 4–6 hours
Sheet 12: General Notes Import boilerplate text + edits 2–3 hours
Sheet 13: Details Standard wall/roof details (from library) 3–5 hours
TOTAL 55–80 hours
Key Assumptions
Entry-Level Speed:
Familiar with Revit but may need time for troubleshooting.
Uses preloaded families/templates (no custom modeling).
Input Clarity:
Existing drawings or field measurements are provided and clear.
No major design changes during drafting.
Exclusions:
Not responsible for structural/engineering details (e.g., beam calcs).
No permit revisions (only base drafting).
Workflow Tips to Save Time
Use Revit Templates: Pre-set layers, title blocks, and schedules.
Batch Processes: Generate schedules/elevations with Revit’s automation.
Focus on Critical Sheets: Prioritize floor plans/elevations (Sheets 2–4) first.
Realistic Completion Timeline
Full-time (40 hrs/week): 1.5–2 weeks (with review/edits).
Part-time (20 hrs/week): 3–4 weeks.
___________________________________________
Possible estimates:
| Method | Rate | Calculation | Total Estimate |
|---|---|---|---|
| Hourly Rate | $50–$120/hr (entry-level) | 55–80 hours (estimated drafting time) | $2,750–$9,600 |
| Per Sheet | $100–$350/sheet | 13 sheets | $1,300–$4,550 |
| Per Square Foot | $0.35–$2.50/SF | 3,006 SF | $1,052–$7,515 |
Service Fee
-------------------------------------------
Base Fee (13 sheets in Revit) $3,500–$4,500
- Includes: Site plan, floor plans, elevations, demolition plan
- Excludes: Structural engineering, permit submissions
Optional Add-ons:
- Field measurements +$1,000
- 3D renderings (2 views) +$800–$1,500 :cite[1]
- Expedited turnaround (50%) +$1,000
____________________________________________
POSSIBLE A
SERVICES
- Redraw 13 architectural sheets in Revit (based on provided as-builts).
- Focus: Floor plans, elevations, demolition plan, schedules (Sheets 1–13).
FEE STRUCTURE
- Rate: $45/hour × 45 estimated hours = $2,025 total.
- Included:
- 2 rounds of client revisions.
- PDF + Revit file delivery.
- Excluded
- Field measurements (if needed: +$750).
- Permit submittals or engineer coordination.
PAYMENT SCHEDULE
- 50% deposit ($1,012.50) to start.
- 50% upon delivery.
Note A:
Track hours meticulously (use Toggl or Clockify).
Communicate limits upfront:
"This quote assumes no major redesigns. If the scope changes, we’ll discuss adjustments."
________________________________________________________________________
Risk:
If the project runs over 45 hours (e.g., due to unclear as-builts or revisions), your effective rate drops further.
Local firms charge $80–$120/hr for similar work
_________________________________
Site Assessment & Existing Conditions Verification : 200 usd flat rate
______________________________________________
Proposal Alpha
Site Assessment & Field Work $100 (flat)
Drafting (13 sheets × 3.5 hrs) 45.5 hrs × $35 = $1,592.50
Total Estimate $1,692.50
You can round it up slightly for a clean number:
Final Estimate: $1,700
_________________________________________________________________
Proposal Beta
Scope of Work
Prepare a full 13-sheet architectural set in Revit, based on the provided hand-drawn site plan and limited documentation. Includes:
-
Site Plan (Sheet 1)
-
Floor Plans
-
Elevations (N, S, E, W)
-
Demolition Plan
-
Foundation & Roof Plan
-
Framing Plans
-
Building Sections
-
Door, Window, and Finish Schedules
-
Electrical Plan
-
Construction Notes & Details
All drawings will be prepared in permit-ready format (no engineering or MEP stamps included).
Fee Structure
| Description | Amount |
|---|---|
| Site Visit & Existing Conditions Review | $100 flat |
| Drafting (13 sheets × avg. 3.5 hrs @ $50/hr) | $2,250 total |
| Total Estimate | $2,350 |
_____________________________________________
When to Adjust Your Rate
If the client balks at $50/hour:
Offer a per-sheet discount ($175/sheet × 13 = $2,275).
Or reduce to $45/hour but strictly cap at 45 hours ($2,025).
If they demand a lower rate:
“I can do $45/hour if you provide perfectly clear as-builts and limit revisions to 1 round.”
______________________________
Final Proposal Recommendation:
For this 4-plex fire repair drafting project, charge $50/hour × 45 hours ($2,250 total)—a fair rate for your 3rd-year ASU skills in San Diego. Include:
13 Revit sheets (permit-ready, no engineering).
2 revision rounds; extra hours at $50/hour.
$100 flat fee if field measurements are needed.
Why?
Balances market rates ($50–$75/hr for juniors).
Protects against scope creep (cap at 45 hours).
50% deposit ($1,125) secures your time.
Alternative: Offer $200/sheet ($2,600 fixed) if hourly pricing worries the client. Always use a contract.
__________________________________
Based on the scope, timeline, and your drafting skill level, a $50/hour rate is fair and competitive. The total estimate of $2,350, including site verification and 13 Revit sheets, reflects both your time and the project’s complexity. You’ve outlined clear deliverables, boundaries, and revision limits, which protects you and builds client trust. This proposal presents a professional, transparent foundation for your first freelance architectural project—and positions you for future work with confidence and credibility. You're ready. Send it.
No comments: